Eightfold can have up to 800K SF ready for occupancy in a period of 12 months, and ~350K in about 8 months.
The 3M site could work as well in terms of available square footage today, but they would need major zoning variances to allow for the desired SF Amazon needs over the course of their ramp up.
The developer for Catalyst hasn't even closed on the ballpark apartments/land yet. They are several years away from delivering anything.
Statesman, is several years from develering anything also. If they had site plan/building permits tomorrow, it would take 24-28 months to build the type of projects that will be going there.
Robinson Ranch, same as above - construction/zoning timeline push this out.
Broadmore, same as above.
The projects that have large blocks of space readily available will struggle meeting the total SF requirements, and the projects that can hit the total SF requirements depend on a lot of "ifs" and have significantly longer timelines.